[1]杨夏,陶飞达,殷栢辉,等.考虑机组进相调节代价的小水电站电抗器配置方法[J].电力电容器与无功补偿,2017,38(6):144-149.[doi:10.14044/j.1674-1757.pcrpc.2017.06.028]
 YANG Xia,TAO Feida,YIN Baihui,et al.Reactor Configuration Method for Small Hydropower Station Considering Leading Phase Adjustment Cost of Generating Unit[J].Power Capacitors & Reactive Power Compensation,2017,38(6):144-149.[doi:10.14044/j.1674-1757.pcrpc.2017.06.028]
点击复制

考虑机组进相调节代价的小水电站电抗器配置方法()
分享到:

《电力电容器与无功补偿》[ISSN:1674-1757/CN:61-1468/TM]

卷:
38卷
期数:
2017年第6期
页码:
144-149
栏目:
清洁能源领域应用技术
出版日期:
2017-12-20

文章信息/Info

Title:
Reactor Configuration Method for Small Hydropower Station Considering Leading Phase Adjustment Cost of Generating Unit
作者:
杨夏1陶飞达1殷栢辉1曾振达1李桂昌2
1. 广东电网有限责任公司河源供电局,广东 河源 517000; 2. 广州市奔流电力科技有限公司,广东 广州 510670
Author(s):
YANG Xia1TAO Feida1YIN Baihui1ZENG Zhenda1LI Guichang2
1. Heyuan Power Supply Bureau of Guangdong Power Grid Inc., Heyuan 517000, China;2. Guangzhou Benliu Power Electrical Engineering Technology Co., Ltd., Guangzhou 510670, China
关键词:
调节代价 小水电 遗传算法 电抗器 无功补偿
Keywords:
adjustment cost small hydro power genetic algorithm reactors reactive power compensation
DOI:
10.14044/j.1674-1757.pcrpc.2017.06.028
文献标志码:
A
摘要:
针对小水电接入在丰水季节容易导致配电网出现电压严重偏高的问题,本文提出了考虑机组进相调节代价的小水电站电抗器配置方法,首先求解出小水电站不装设电抗器时的机组进相调节代价,其次建立考虑机组进相调节代价的小水电站电抗器配置数学优化模型,并借助遗传算法对其进行求解;最后,根据求解结果,结合不安装电抗器时的机组进相调节代价判断小水电站电抗器的配置。仿真算例表明,方法切实可用,可为小水电站电抗器容量的合理配置提供依据。
Abstract:
For the high voltage problem of distribution network caused by small hydropower in the wet season, the reactor configuration method for small hydropower station considering the leading phase adjustment cost of unit is proposed in this paper. Firstly, the leading phase adjustment cost of small hydropower without reactor is obtained. Then, the mathematical optimization model for reactor configuration of small hydropower station considering the leading phase adjustment cost of unit is considered and is solved with help of genetic algorithm. Finally, the reactor configuration of small hydro power station is judged in accordance with the solving result and with combination of the leading phase adjustment cost of the unit without installing reactor. It is shown by the simulation calculation that the method is practical and can provide evidence for the reasonable configuration of the reactor of small hydro power station.

参考文献/References:

[1] 刘艺, 叶胜, 彭显刚, 等. 小水电群区域电网电压优化控制的应用探讨[J]. 电力系统保护与控制, 2010, 38(9):136-140.
LIU Yi, YE Sheng, PENG Xiangang, et al. Voltage optimal control research on small hydropower stations group in regional power grid[J]. Power System Protection and Control, 2010, 38(9):136-140.
[2] 栗祥. 小水电并网无功不足及其改善措施[J]. 科技创新导报, 2011(8):67-67.
[3] 张聪慧. 含小水电的区域电网优化运行研究[D]. 广州:广东工业大学, 2010.
[4] 孙元. 含小水电接入的区域配电网电压问题分析与优化控制研究[D]. 南京:东南大学, 2015.
[5] 李劲, 唐捷, 张勇军, 等. 小水电群对配电网无功电压影响机理分析[J]. 南方电网技术, 2012(5):39-42.
LI Jin, TANG Jie, ZHANG Yongjun, et al. Mechanism analysis on the effect of small hydropower plant group on the reactive voltage of distribution network[J]. Southern Power System Technology, 2012(5):39-42.
[6] 张锡填. 广东电网无功电压调控的典型问题及对策研究[D]. 广州:华南理工大学, 2014.
[7] 韦延方, 卫志农, 张友强, 等. 发电机进相运行的研究现状及展望[J]. 电力系统保护与控制, 2012, 40(9):146-154.
WEI Yanfang, WEI Zhinong, ZHANG Youqiang, et al. Progress and development trend on leading phase of generator[J]. Power System Protection and Control, 2012, 40(9):146-154.
[8] 王丽莉. 小水电引起配电网高电压问题的解决方案[J].浙江电力, 2011, 30(7):57-60.
WANG Lili. Solution to high voltage problem in distribution network due to small hydropower[J]. Zhejiang Electric Power, 2011, 30(7):57-60.
[9] 张洪兰. 小水电系统电压无功问题及控制方案研究[D].北京:华北电力大学, 2010.
[10]BAI Yaopeng, XU Lijie, WANG Wei, et al.Study on reactive power and voltage control of power grid with small hydropower[C]//2010 International Conference on Electrical and Control Engineering, 2010:5647-5650.
[11]CELSO B, TISCHER,FABIO C, POSSER,LUCAS G, SCHERER, et al.Hybrid method for control of voltage regulation applied in micro hydro power station[C]//IECON 2012 38th Annual Conference of the IEEE Industrial Electronics Society, 2012:1013-1018.
[12]丁伯剑, 杨静, 吴桂滨, 等. 含小水电配电网的感性无功配置方法[J]. 电力需求侧管理, 2013(2):16-18.
DING Baijian, YANG Jing, WU Guibin, et al. Reactive power configuration for distribution networks with small hydropower plants[J]. Power Demand Side Management, 2013(2):16-18.
[13]王文华, 魏博, 朱广明, 等. 抑制分布式小水电配电网稳态过电压的无功配置方法[J]. 高压电器, 2015(11):97-102.
WANG Wenhua, WEI Bo, ZHU Guangming, et al. Reactive power configuration method for suppressing steady overvoltage of distributed power distribution network with small hydropower plants[J]. High Voltage Apparatus, 2015(11):97-102.
[14]张锡填, 张勇军. 10 kV并联电抗器在含小水电配电网中的优化方法[J]. 水电能源科学, 2013(10):217-220.
ZHANG Xitian, ZHANG Yongjun. Optimal method of 10 kV parallel reactors in distribution network with small hydro power[J]. Water Resources and Power, 2013(10): 217-220.
[15]庞明月, 张力小, 王长波. 基于生态能量视角的我国小水电可持续性分析[J]. 生态学报, 2014, 34(3):537-545.
PANG Mingyue, ZHANG Lixiao, WANG Changbo. The sustainability analysis of small hydropower plants in China based on ecological energetic accounting[J]. Acta Ecologica Sinica, 2014, 34(3):537-545.
[16]程夏蕾, 朱效章. 中国小水电可持续发展研究[J]. 中国农村水利水电, 2009(4):112-118.
[17]白耀鹏. 小水电接入电网对系统运行影响的研究[D].北京:北京交通大学, 2010.

备注/Memo

备注/Memo:
收稿日期:2016?12?26.作者简介: 杨夏(1982—),女,工程师,主要从事配电网自动化与无功优化方面的研究工作。 陶飞达(1984—),男,高级工程师,主要从事配电运行及电压质量管理工作。 殷栢辉(1986—),男,工程师,主要从事电网可靠性及电能质量管理方面的工作。 曾振达(1984—),男,工程师,主要从事配电网运行管理分析等工作。 李桂昌(1990—),男,助理工程师,主要从事电网规划、无功优化等工作。
更新日期/Last Update: 2017-12-10