LIU Gengen, WEI Junmei, BAI Wei, et al. Discussion on First Commissioning Failure in Offshore Wind Power Station[J]. Power capacitor & reactive power compensation, 2025, 46(3): 106-112.
LIU Gengen, WEI Junmei, BAI Wei, et al. Discussion on First Commissioning Failure in Offshore Wind Power Station[J]. Power capacitor & reactive power compensation, 2025, 46(3): 106-112. DOI: 10.14044/j.1674-1757.pcrpc.2025.03.014.
This paper introduces two typical cases of abnormal switch tripping during the first delivery of offshore wind power stations. Through the in-depth analysis
the reason for abnormal switch tripping in Guangxi offshore wind power station is due to the closing of no-load transformer generates excitation current
three-phase current value difference is large
resulting in zero sequence current exceeds the preset value of the protection; the reason for abnormal switch tripping in Zhejiang offshore wind farm is due to the long cable capacitance
closing the no-load transformer
causing series resonance
resulting in the current differential protection start. Taking proper measures to avoid the accident from happening again. This is a reference for commissioning of future offshore wind power projects.