Reason Analysis and Precautionary Measures for A 35 kV Shunt Capacitor Bank Explosion
更新时间:2024-09-14
    • Reason Analysis and Precautionary Measures for A 35 kV Shunt Capacitor Bank Explosion

    • POWER CAPACITOR & REACTIVE POWER COMPENSATION   Vol. 39, Issue 1, Pages: 23-27(2018)
    • DOI:10.14044/j.1674-1757.pcrpc.2018.01.005    

      CLC: TM53
    • Published:2018,

    移动端阅览

  • HUANG BIN, LI HAO, XU SHANSHAN, et al. Reason Analysis and Precautionary Measures for A 35 kV Shunt Capacitor Bank Explosion. [J]. Power capacitor & reactive power compensation, 2018, 39(1): 23-27. DOI: 10.14044/j.1674-1757.pcrpc.2018.01.005.

  •  
  •  

0

Views

80

下载量

8

CSCD

Alert me when the article has been cited
提交
Tools
Download
Export Citation
Share
Add to favorites
Add to my album

Related Articles

The New Problems Come from Capacitor Bank with Microcomputer protection
Analysis of Failures of Relay Protection Installation for Capacitor Bank in Xing cheng Substation
Inspections on Construction Quality of the Shunt Capacitor
Analysis of Parallel Resonance of Reactive Power Compensation Shunt Capacitor Bank
Analysis and Measure of Parallel Assembling Capacitor with Malfunction and Abnormal Operation

Related Author

ZHOU Cun-he
Dong Yuejun
Wang Shuhui
Ren Hongchang
CHEN Jing-yuan
WANG Wei-yi
SHENG Xiao-wei
HUANG Mei

Related Institution

Guilin Power Capacitor General Works
  唐山供电公司 河北唐山063000  
Tangshan power supply company, Hebei Tangshan China
Tangshan Electric Energy Supply Company
  北京交通大学电气工程学院 北京100044  
0