YU JINSONG, SUN WEN, MENG CHAO, et al. Formulation and Implementation of Transcontinental Overhaul of Domestic-made 500 kV SC. [J]. Power capacitor & reactive power compensation, 2021, 42(5): 7-13.
DOI:
YU JINSONG, SUN WEN, MENG CHAO, et al. Formulation and Implementation of Transcontinental Overhaul of Domestic-made 500 kV SC. [J]. Power capacitor & reactive power compensation, 2021, 42(5): 7-13. DOI: 10.14044/j.1674-1757.pcrpc.2021.05.002.
Formulation and Implementation of Transcontinental Overhaul of Domestic-made 500 kV SC
摘要
2016年5月18日
国家电网公司首个海外大型绿地输电特许权项目—巴西特里斯皮尔斯输电项目顺利投运。项目中在500 kV Paranaita变电站和500 kV Rio Verde变电站投运的5套500 kV串联电容器补偿成套装置是我国迄今为止已投入商业运营、加装装置套数最多、工程量最大、累计容量最大的海外串联电容器补偿工程。经过首个设备大修周期的稳定运行后
the first large-scale overseas green field power transmission concession project of State Grid Cooperation of China
the Brazilian Tries Pierce Power Transmission Project
was successfully put into operation. So far
the 5 sets of 500 kV series compensation capacitor complete sets(“SC”for short)operated at 500 kV Paranaita substation and 500 kV Rio Verde substation is our series capacitor compensation project abroad in commercial operation
with the largest number of installed units
the largest project volume and the largest accumulated capacity. After the stable operation of the overhaul cycle of the first equipment
China and Brazil worked closely in 2019 to carry out intercontinental coordinated overhaul work in batches on these 5 sets of SC as planned. As for the planned overhaul this time
the strict overhaul program is made in accordance with the technical feature of the equipment and the operation and maintenance record over the years.The overhaul work has been finished as the plan
the key performance of the whole equipment has been inspected and the potential operation risk of the series compensation device has been eliminated
which lays the foundation for the safe and stable operation of the next overhaul cycle of the equipment.