[1]胡畔,陈红坤,朱晓航,宋梦琼.计及电能质量约束的高铁负荷接入主网规划[J].电力电容器与无功补偿,2016,37(06):46-52.
HU PAN, CHEN HONGKUN, ZHU XIAOHANG, et al. Integration Planning of High-speed Traction Load Taking Power Quality Constraints Into Account. [J]. Power capacitor & reactive power compensation, 2016, 37(6): 46-52.
[1]胡畔,陈红坤,朱晓航,宋梦琼.计及电能质量约束的高铁负荷接入主网规划[J].电力电容器与无功补偿,2016,37(06):46-52. DOI: 10.14044/j.1674-1757.pcrpc.2016.06.009.
HU PAN, CHEN HONGKUN, ZHU XIAOHANG, et al. Integration Planning of High-speed Traction Load Taking Power Quality Constraints Into Account. [J]. Power capacitor & reactive power compensation, 2016, 37(6): 46-52. DOI: 10.14044/j.1674-1757.pcrpc.2016.06.009.
由于大量工程项目规划阶段未预先考虑可能引起的电能质量问题
非线性污染性负荷的大规模接入易引起系统严重的电能质量问题。本文从铁路部门及电网的利益主体出发
以双方电能质量指标为约束条件
考虑主网变电站间隔投资成本
提出了一种在规划阶段适用于主网的高铁负荷接入方法。结合高铁牵引负荷的功率不确定概率模型
利用蒙特卡洛法及直流潮流法
建立了高铁负荷概率潮流分析模型。针对高铁负荷特性
以双方电能质量指标为约束条件
建立了以投资费用最小为目标的高铁接入电网机会规划约束模型
并采用线性递减粒子群算法对该模型进行求解。最后
以贵州某实际高铁建设工程对该线路接入电网规划方案进行了实例研究。仿真结果表明
某些供电距离较短、短路容量较大的110 k V变电站能够满足高铁供电要求。
The serious power quality problem is likely caused by the large scale-integration of nonlinear pollution load due to the power quality problem not considered in advance in the planning stage of large projects. In this paper
a kind of high speed rail load integration method which is suitable for the main network at planning stage is proposed at such condition as the interest of railway department and power network
the power quality index as constraint condition of both parties and the investment cost of substation bay of main power network. The load probability flow analysis model of high speed rail is established with combination of the uncertainty probability model of traction load of high speed rail and with the use of Monte Carlo and DC power flow methods. As for the load feature of high speed rail and the power quality index of both parties as constraint condition
the chance planning constraint model of high speed rail to the power network with minimum investment as objective is established and the planning model is solved by LDIW-PSO algorithm. Finally
real example of the planning scheme of the line to the power network at certain practical high speed rail construction project is performed. It is shown by the simulation result that some 110 k V substations with shorter power supply distance and bigger short circuit capacity can meet the power supply requirement of high speed rail.
高铁负荷主电网规划电能质量约束概率潮流分析机会约束模型
load for high speed railprimary power planningpower quality constraintsprobability flow analysischance-constraint model