LI JIHONG, WU XINGLONG, ZHANGXIAODI, et al. Simulation Study on Switching Process of Reactive Power Equipment at DC Converter Station. [J]. Power capacitor & reactive power compensation, 2020, 41(1): 38-44.
LI JIHONG, WU XINGLONG, ZHANGXIAODI, et al. Simulation Study on Switching Process of Reactive Power Equipment at DC Converter Station. [J]. Power capacitor & reactive power compensation, 2020, 41(1): 38-44. DOI: 10.14044/j.1674-1757.pcrpc.2020.01.007.
Determining reasonable reactive power balance and switching strategy of the converter station is the basis for safe and stable operation of the HVDC transmission system.In this paper
the reactive power demand of AC/DC systems and the capacity determination of reactive power compensation equipment are described.The CDC6 DC quasi-steady state model is established in the PSS/E software
and its self-defined analysis function is used to simulate the reactive power switching strategy of the converter station with both inductive and capacitive reactive power compensation equipment from such two aspects as start-up and outage of the DC system.The start-up process follows the principle of firstswitching-out inductive reactive power equipment
followed by switching-in capacitive reactive power equipment
while the stop process follows the principle of firstswitching-out capacitive reactive power equipment
followed by switching-an inductive reactive power equipment.Finally
through the simulation example
the reactive power exchange between the converter station and the AC system is always within the limited range
which verifies the effectiveness of the method.
关键词
直流模型PSS/E感性无功容性无功无功投切策略
Keywords
DC modelPSS/Einductive reactive powercapacitive reactive powerreactive switching strategy